Portal de Los Alcazares

www.portaldelosalcazares.com

Los Alcazares - SpanishLos Alcazares - English
detail of Los Alcazares

 

The Community hands over to the Los Alcázares City Council the project for the new rainwater collector to receive municipal approval (08/07/2020)

| The regional government is going to invest 2 million for the construction of the 971 meter collector that will allow capturing 7.12 m3 / s, minimizing the impact of the rains in the center of the town | The Community has delivered to the Los Alcázares City Council the project for the new rainwater collector, once its drafting is finished, with which it is intended to minimize the impact of the rains in the center of the municipality, as the regional government promised last month of January. This was announced today by the Minister of Water, Agriculture, Livestock, Fisheries and the Environment, Antonio Luengo, during the presentation of the action, while explaining that "the project needs to receive municipal approval so that we can start the tender." As explained by Luengo, "the City Council must now approve the project in the Local Government Board, make the land available to the Community for the execution of the work, as well as show the commitment to receive the actions once they are completed, to guarantee their maintenance and exploitation by integrating it into the network of municipal collectors ".

Once the Ministry receives the approval of the project from the City Council, "the works are expected to be tendered in September and will have an execution period of 5 months." The total investment budget amounts to 1,998,285 euros. "This is one of the actions that the Community is planning to minimize the impact of the rains in the municipality and reduce flooding in the area, and in the coming weeks we will present new initiatives that will benefit the town and the protection of the Mar Menor "explained the counselor Antonio Luengo. Luengo explained that it is going to act in 971 meters.

The works begin in Labrador street, collecting rainwater from the area outside the urban area and, after crossing the school and Jaén street, passes through Orense, Joaquín Blume streets and 13 de Octubre avenue until joining the Avenida de La Libertad to Calle Telegrafos ". The project consists of three sections of precast reinforced concrete drawers.

It will run entirely under the carriageways, with their corresponding manholes, changes of direction, drains and transverse rains for collecting rainwater, and its collection capacity will be 7.12 m3 / s.

In addition, the pavement of the affected streets and all the services existing on its layout will be replaced.

Source: CARM

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información